Bayernwerk Netz · E.DIS Netz · SH Netz (E.ON)
Large parts of Bavaria, Brandenburg and Mecklenburg-Western Pomerania, Schleswig-Holstein · Pilot since 13 Aug 2026
How it works
Criteria-based allocation in semi-annual cycles. Applications are collected in the window, scored automatically and ranked; the grid compatibility assessment then follows this ranking. Ties at the same grid point are decided by lot. The submission time within the window does not matter.
Who must take part
Battery storage with more than 300 kW offtake/charging capacity and offtake customers above 1,000 kW (medium and high voltage).
Who is exempt
Household customers, green-power-only storage, generation-only plants and privileged public-service customers (e.g. hospitals, emergency services, schools) — first come, first served still applies to them.
Dates
- 12 Oct 2026Application portal opens, window starts
- 23 Nov 2026Window closes (documents + deposit)
- 15 Mar 2027Allocation feedback
- 10 May 2027Latest refund of the delivery deposit
Criteria
- Project maturity · max. 10 points
Planning and permitting status at the time of application (incl. land security, permits, delivery horizon). - Contribution to regional scenario (Sec. 14d EnWG) · max. 10 points
How much the project supports the regional targets of grid planning. Technologies already exceeding regional quotas score lower. - Co-location with renewable plant · max. 10 points
Shared use of a grid connection point with a renewable energy plant. - Flexibility commitment · max. 10 points
Willingness to sign a flexible connection agreement (capacity curtailment during congestion). According to law-firm reports the declaration is already requested in the application form. - Local infrastructure dependency · max. 10 points
Reliance on local water, heat, transport, gas or data infrastructure. - Existing grid connection point · max. 10 points
Use of an existing connection point or site-specific investments already made.
Documents
- Complete application in the new portal (no automatic transfer of old portal applications)
- Delivery deposit: EUR 1,500/MW net (per the procedure description, as cited by MASLATON)
- Evidence of project maturity (land security, permitting status)
- Declaration on the flexible connection agreement
Pitfalls
- Since 13 Aug 2026 the old connection portal no longer accepts affected projects — anyone who has not switched loses the cycle.
- After allocation, according to MASLATON, there are only eight weeks (non-extendable) to prove full land availability — otherwise the reservation lapses.
- The exact scoring per criterion is not fully public. The self-check below is therefore an orientation, not a score forecast.