BESS-Market
Project Database · Sachsen-Anhalt

Battery storage in Sachsen-Anhalt.

All battery storage units ≥ 1 MW registered in Sachsen-Anhalt: 551 MW in operation, 641 MW planned.

In operation (power)

551 MW

32 units

In operation (capacity)

1.09 GWh

Planned (power)

641 MW

34 units

Planned (capacity)

1.34 GWh

Largest units

  1. ECO POWER THREE
    Staßfurt, Sachsen-Anhalt · In Planung
    300 MW
    600 MWh
  2. Stendal BESS
    Stendal, Sachsen-Anhalt · In Betrieb
    105 MW
    209 MWh

Recently commissioned

    Recently registered (planned)

    • BESS Bernburg
      Bernburg, Sachsen-Anhalt · 15 MW / 30 MWh · planned 23/09/2026

    Source: Marktstammdatenregister (Bundesnetzagentur), battery storage ≥ 1 MW. As of 21/09/2026.

    All battery storage units ≥ 1 MW

    Loading full list …
    2 units · 405 MW · 809 MWh
    UnitLocationMWMWhhStatusCOD / plannedOperatorGrid operatorSave
    ECO POWER THREE
    SEE901024459440
    Staßfurt, Sachsen-Anhalt3006002Planned01/02/2027ECO POWER THREE GmbH50Hertz Transmission GmbHSign in to save
    Stendal BESS
    SEE965822398363
    Stendal, Sachsen-Anhalt104.52092In operation30/07/2026Seerose Energie GmbHAvacon Netz GmbHSign in to save

    Source: Marktstammdatenregister (Bundesnetzagentur), storage units with technology "battery" and gross power ≥ 1 MW. Operators that are natural persons are not shown. No guarantee; register data can be reported late or incorrectly.

    Other federal states

    Go to the marketplace

    All listed projects with filters for country, phase, size and grid status.

    Open project marketplace
    • Project ID, country and region
    • Power (MW), capacity (MWh) and storage duration
    • Project phase and grid connection status
    • Planned COD and verification level
    • Transaction options and capital requirement

    Your project in the database?

    List your project and make it discoverable for investors.