Battery storage in Mecklenburg-Vorpommern.

All battery storage units ≥ 1 MW registered in Mecklenburg-Vorpommern: 113 MW in operation, 738 MW planned.

In operation (power)

113 MW

17 units

In operation (capacity)

195 MWh

Planned (power)

738 MW

45 units

Planned (capacity)

2.22 GWh

Largest units

  1. BESS_Sabel
    Hohen Sprenz, Mecklenburg-Vorpommern · In Planung
    210 MW
    1,000 MWh
  2. BESS_Bentwisch
    Bentwisch, Mecklenburg-Vorpommern · In Planung
    150 MW
    300 MWh

Recently commissioned

    Recently registered (planned)

      Source: Marktstammdatenregister (Bundesnetzagentur), battery storage ≥ 1 MW. As of 21/09/2026.

      All battery storage units ≥ 1 MW

      Loading full list …
      2 units · 360 MW · 1,300 MWh
      UnitLocationMWMWhhStatusCOD / plannedOperatorGrid operatorSave
      BESS_Sabel
      SEE967459235615
      Hohen Sprenz, Mecklenburg-Vorpommern2101,0004.8Planned01/01/2027East Energy PV Wiendorf GmbH & Co.KG—Sign in to save
      BESS_Bentwisch
      SEE941869606388
      Bentwisch, Mecklenburg-Vorpommern1503002Planned01/01/2027East Energy PV Rostock GmbH & Co.KGE.DIS Netz GmbHSign in to save

      Source: Marktstammdatenregister (Bundesnetzagentur), storage units with technology "battery" and gross power ≥ 1 MW. Operators that are natural persons are not shown. No guarantee; register data can be reported late or incorrectly.

      Other federal states

      Go to the marketplace

      All listed projects with filters for country, phase, size and grid status.

      Open project marketplace
      • Project ID, country and region
      • Power (MW), capacity (MWh) and storage duration
      • Project phase and grid connection status
      • Planned COD and verification level
      • Transaction options and capital requirement